FG Plans Three-Month Trial Operations for Kaduna-Kano Rail Line Ahead of December Commissioning

Oru Leonard 

The Federal Government is planning a three-month trial operation of the Kaduna-Kano railway corridor to ascertain its readiness for full commercial services ahead of its scheduled commissioning in December.

The Permanent Secretary of the Federal Ministry of Transportation, Engr. Funso Adebiyi, disclosed this during an inspection tour of the railway project, explaining that the exercise would enable authorities to assess the structural integrity, safety and operational capacity of the infrastructure.

Adebiyi said the government was also considering offering passengers free train services throughout the testing period, subject to approval by President Bola Tinubu.

He explained that the trial phase would help identify and address any outstanding technical issues before the railway is opened for regular commercial operations.

Speaking on the progress of the project, the Permanent Secretary said contractors had addressed concerns raised during previous inspections, particularly those relating to passenger safety, lighting and maintenance facilities.

He disclosed that toughened glass initially installed in passenger areas had been replaced with laminated glass to minimise the risk of injuries in the event of breakage.

According to him, laminated glass offers better protection because, unlike toughened glass, it is less likely to scatter into dangerous fragments when damaged.

He added that the lighting system had also been upgraded, with a directive that installed bulbs must have a minimum lifespan of three years.

On maintenance and operational readiness, Adebiyi said arrangements were underway to provide man lifts and build the technical capacity of Nigerian Railway Corporation (NRC) personnel to manage the facilities.

He disclosed that the NRC had been directed to nominate engineers for intensive training in railway station operations, adding that he would personally participate in the training and examination process.

He said only personnel who successfully pass the examinations would be retained for the operational responsibilities before the NRC eventually assumes full management of the railway system.

The Permanent Secretary further revealed that four lifts had been ordered to improve accessibility for persons with disabilities across different sections of the terminal.

On the outstanding railway connection between Jaji and Kaduna, Adebiyi attributed the delay to security challenges and land acquisition requirements, which necessitated the construction of a bridge.

He, however, assured that construction of the bridge was ongoing at the site and had reached an advanced stage.

According to him, the bridge remains the major outstanding component preventing the railway line from extending fully into Kaduna town, expressing optimism that the section would be completed within four to six months.

Looking beyond the Kaduna-Kano project, Adebiyi disclosed that the Federal Government plans to flag off construction of the Ibadan-Osogbo-Ilorin-Minna railway corridor within the next two months.

He also said the proposed Itakpe-Abuja railway extension, forming part of the Itakpe-Warri-Abuja corridor, had reached an advanced stage and was awaiting presidential approval for construction to commence.

Meanwhile, the Director-General of the Debt Management Office (DMO), Patience Oniha, said the inspection was part of the agency’s responsibility to monitor and assess capital projects financed through government funding.

Oniha noted that investments in railway infrastructure would generate economic benefits beyond passenger and cargo transportation, creating opportunities for businesses, traders and small-scale entrepreneurs operating along the corridor.

She explained that improved rail connectivity would stimulate commercial activities and enhance economic opportunities for communities along the route.

On funding for proposed railway projects, the DMO chief said requests would undergo the necessary evaluation, appraisal and approval processes before financial support could be provided.

A representative of the China Civil Engineering Construction Corporation (CCECC), Mark Xu, assured that the company remained committed to completing the project ahead of the planned December commissioning.